Delano Restoration Project

Asphalt paving guide 678x381

City of Muskegon Heights issued the following announcement on Nov 4.

Phase One Start: November 2021 Phase One End: November 2021

Phase Two Start: Spring 2022 Phase Two End: Spring 2022

Investment: $650,000

What Is Being Done?

  • The project involves full depth reconstruction of two lanes of undivided roadway in two phases:
    • Phase One:
      • Asphalt Removal
      • Sidewalk and curb removals
      • Storm sewer improvements
      • Roadway grading and aggregate base
    • Phase Two:
      • Concrete curbs
      • Sidewalk and driveway improvements
      • Asphalt paving and turf restoration
How Traffic Will be Affected:

  • Construction will take place in two phases:
    • Delano Avenue will be temporarily closed during construction between the intersection of Sanford
    • Street to the intersection of Hoyt Street. Residents are encouraged to park on side streets during
    • construction.
    • Traffic to businesses and residents will be maintained utilizing side streets and alleys.
    • Pedestrian traffic will be detoured as necessary during construction.
Original source can be found here.

Source: City of Muskegon Heights

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS